If you’re seeking some quotes from EV charging companies in India for multiple locations, be sure to get each one to demonstrate how it’d use a small pilot and how it would scale up from there. Choose locations with varying parking and demand patterns to identify the impact of the proposal and where it needs to be modified. If an EV charging franchise is included in the deal, ensure that the agreement is applied if there are different opening hours, charge, and public access policies at each individual site.
How to compare EV charging companies on a pilot
Send the same brief to each bidder. Report on the location(s) proposed, the property contacts, likely drivers, hours and constraints. State what you want to learn from the pilot. A property group might consider comparing the public demand at two locations. If there are multiple offices in a business, then they may wish to see if one provider can provide a single policy for multiple car parks. Record the questions before deciding on what to measure.
Select locations with varying conditions.
As a representative deployment, a retail business chooses one store in the town centre that sees shorter parking times and a different one with longer parking time. The main purpose of the town-centre site is to determine if drivers are able to charge enough during a short stop. At the second location, it is evaluated if additional people will plug in if they were already planning to stay. Power requirements, operating hours and instructions may vary between the sites, even if they have the same reporting system.
Do not select the property that has the best wiring path and the most enthusiastic owner of the property. This can make the pilot launch easy, but with some properties remaining unknown. Add a site with the constraint is in the portfolio, e.g. deliveries are limited because of another site in the portfolio that has limited evening access. Include its survey results in the pilot brief. The NITI Aayog Implementation Handbook has covered the aspects of site planning and matching charging demand with infrastructure. It is available in both English and French.It is bilingual (English and French).
Request a Rollout Plan from Each Provider to Compare
Request a common list of deliverables at each site. Inquire with the supplier of what can be done at the central level, what can be done at the local level, and what the property managers need to arrange. If the provider requires you to sign for other sites before you can see them, ask which locations and what costs that will be covering the signing.
Decision area
- The measure to be used in the trial
- What to validate when rolling out wider.
- Installation
- Quoted and actual scope, open dependencies and handover quality
- A person is responsible for checking each site and giving permission for changes.
- Station use
- You can now get away with paid sessions, energy delivered and failed attempts.
- The use of demand information to direct equipment at another site
- Support
- Responding to customer tickets, recording restoration history and repeating faults
Field engineers and parts will be available:
Reporting
The report of sessions and payout/costs is available.
Common location IDs and reporting. Common location IDs and reporting on portfolios.
Property operations
Blocked bays, access complaints, and staff workload
What are the rules that can be local, and who does the approval?
Share the same pilot brief with the other EV charging companies on your shortlist and request that each company respond to how it will help the next set of properties.
Confirm if the bid is split between central and local work.
Request the bidder to provide access to software, support for software quality, and shared reporting. At the site level, identify the parking permit holders, utility discussions, and the installation calendar. Coordinating the work can be done by one national point of contact. It’s still valuable to have an idea of what field team covers which address and what would happen if a technician required a spare.
Compare Results Site by Site
Apply the same operating hours, availability, and completed sessions definitions. If one place opened after another, or there were access problems, record this in the review. The overall figure for the pilot can mask significant differences. For instance, if a site uses a lot at the outlet, it will compensate for barely any use of another outlet, even if the latter is the closer match to most of the outlets you are looking to purchase more uses on.
Get the financial folks to check local costs and settlements individually before considering the overall figure. An illustrative supplier can charge a common software fee on the properties and expect the hosts to pay site-specific electricity and repair costs. Request prices based on location and a sample consolidated report. Verify its ability to react to a change in the opening date of one site or its temporary closure.
Decide beforehand on what constitutes a good reason to expand
Agree on the conditions for three choices. Extend if the pilot is successful and if sites share key features. Adjust the plan if issues are fixable, such as signage, a slow support handoff, or a poor bay position. Hold when evidence raises a larger question, such as the local demand or reliable electrical capacity at multiple properties. Make a brief note of what was different and why before granting permission to the next set.
Record the carryover changes.
Record in brief the modification changes that were implemented in the pilot that were successful and can be applied at other sites. A new or updated support script/bay sign may be appropriate throughout the portfolio. You might need to use another charger type or power setting that will only fit on the site where it was tested. Have a discussion with the provider about the difference, and incorporate changes into the quote for the next group. This provides local managers with a good justification for any deviations from the original plan.
Renew or Expand Using the Evidence From Each Property
When evaluating an EV charging franchise, choose providers that can show how their proposal fits more than one type of location. Keep the data from each site visible, resolve recurring problems during the pilot and confirm local support at the next addresses. A staged rollout lets the property group apply what it has learned before ordering equipment for sites it has yet to test.
Frequently Asked Questions
Is the same charger model required for all locations?
When sites cater to the same kind of drivers, a standard model can make training easier and reduce spare part costs. Before setting it as the default, make sure the vehicles are compatible, that the dwell time is available and that supply is available at each property.
What’s a good time for a pilot?
Provide adequate operating time at each location to demonstrate normal demand, peak periods and support workload. Proceed with any segments of the trial which may be closed due to temporary closure or seasonal events, or repeat segments of the trial if they were conducted and found unrepresentative.
Is it okay to apply the same customer price for all properties?
Explain the factors that influence the price and which prices are set by who, and how do local prices, costs, hours and parking affect the price? Develop a strategy for individual pricing decisions that remain with the central team.
Can a single vendor manage installations across different states?
Ask for evidence of coverage at your exact locations. Confirm the local installation and support teams, the utility responsibilities and how the vendor handles differences between properties.
Which documents should site managers receive?
Give them the final bay plan, charging and parking rules, support contacts, operating instructions and escalation process. Ensure they know where to retrieve the site’s service records.